Supreme Court of Canada

Lease and hire of work—Work by contract—Fixed price—Cancellation at will of owner—Indemnity of the workman—Damages—Art. 1691 C.C.

Article 1691 of the Civil Code of Quebec gives the owner the right to cancel at his own will a “contract for the construction of a building or other works at a fixed price, although the work has been begun,

[Page 21]

on indemnifying the workman for all his actual expenses and labour, and paying damages according to the circumstances of the case.”

Held that the obligation to indemnify the workman for all his actual expenses and labour, to wit, to pay him for the work done, is absolute; and the liability for damages depends on the circumstances of each particular case. But the workman cannot demand, as damages, payment in full as if the work had been entirely performed.

APPEAL from the decision of the Court of King’s Bench, appeal side, province of Quebec, maintaining, in part an appeal to that court by the respondents and dismissing a cross-appeal by the appellants.

The material facts of the case are sufficiently stated in the judgment now reported.

C. A. Barnard K.C. and W. F. Chipman K.C. for the appellant.

A. R. McMaster K.C. and L. J. Béïque K.C. for the respondents.

The judgment of the court was delivered by

Mignault J.—This is an appeal from a judgment of the Court of King’s Bench, province of Quebec, modifying, by reducing the amount awarded, a judgment of the Superior Court which had granted the present appellant $35,000, under the contract to which I will presently refer. At the same time, the Superior Court rejected a claim of the appellant for $25,000, as damages for loss of profit, and as to this claim its judgment was upheld. The appellant now appeals to this court on both points.

The material facts of the case are as follows.

In 1920, the respondent had a ship under construction at Three Rivers by the Three Rivers Shipyards, Limited. This company went into liquidation before the work was finished, and the respondent then entered into an agreement with the appellant to complete the construction of the ship. This agreement, signed by the respondent in December, 1920, and by the appellant in March, 1921, contained the following covenants:—

Whereas the company (the respondent) are the owners of a ship commonly known as an oil tanker of approximately 6,500 tons deadweight now partially constructed in the yard of the Three Rivers Shipyards Company, Three Rivers, Quebec, and through their representative have mutually agreed with the shipbuilders (the appellant) to complete this vessel

[Page 24]

ers, engines and machinery. The trial of both actions, which had been consolidated, took place at Three Rivers. We were informed by the parties that at the argument on the first action, the one asking for cancellation, the appellant admitted that under art. 1691 of the civil code the respondent was entitled to cancel the agreement, and this point of view was accepted by the learned trial judge who pronounced the agreement duly cancelled. The appellant states that it acquiesced in the judgment in this action and paid the costs. In the second action, the learned trial judge awarded the appellant the $35,000, but rejected the claim for $25,000 for want of proper proof. Both parties appealed from this judgment to the Court of King’s Bench. The latter court affirmed the judgment of the Superior Court in so far as the claim for $25,000 was concerned, but modified it in regard to the item of $35,000, Which it reduced to $12,000, the respondent in its factum having expressed its willingness to pay the latter sum. The appellant now comes before this court asking that the judgment of the Superior Court be restored as to the award of $35,000, but reversed in respect of the other item of its demand.

The only judgment before us is that rendered in the appellant’s action claiming $35,000, under clause 8 of the agreement and $25,000 damages for loss of profit under clause 7.

The appellant in its factum as well as in its argument before us, endeavoured to take the position that art. 1691 C.C. did not apply to the agreement in question, or, if it . did, it was only with respect to the installing of the boilers, engines and machinery. Had the appellant taken that position before the trial court, it is likely that the learned trial judge would have made a finding on the question whether the appellant had fulfilled its contractual obligations, and whether the respondent had valid cause for cancelling the contract. The admission of the appellant that the case came within the scope of art. 1691 C.C., while to some extent an admission of law rather than of fact, no doubt influenced the course of the trial and the judgment. I am not disposed therefore to deal with the litigation on any other basis. Much of the evidence adduced at the trial is irrelevant on an issue governed by art. 1691 C.C.

[Page 25]

The respondent, on the other hand, led considerable evidence to show that the contract had become impossible of performance for the reasons alleged in its protest, i.e., that the ship, for lack of sufficient depth in the channel of the St. Maurice, could not be brought to the appellant’s shipyards for installation of the boilers, engines and machinery, or removed therefrom after the work was done. The testimony on this point is contradictory, and I am not satisfied that the respondent, which had the onus of establishing it, has shewn beyond doubt that performance of the contract had become impossible within the meaning of art. 1202 C.C. Moreover, the most that could be said is that, if the performance of the contract became impossible, it was through no fault of the appellant, Which clearly could not be expected to dredge the bed of a navigable stream, and therefore the respondent would be bound to the extent of the benefit received by it. I prefer therefore to rest nothing on the alleged impossibility of performance, but I will view the case as being one calling for the application of art. 1691 CC

This article gives the owner the right to cancel at his own will a contract for the construction of a building or other works at a fixed price, although the work has been begun,

on indemnifying the workman for all his actual expenses and labour, and paying damages according to the circumstances of the case.

The obligation to indemnify the workman for all his actual expenses and labour, to wit, to pay him for the work done, is absolute. Liability for damages depends on the circumstances of each particular case. The workman is certainly entitled to payment for the work actually done and money expended by him, and the circumstances of the case may also, as a matter of justice, give him the right to claim damages.

It would be quite impossible, in my opinion, to say that the workman can demand, as damages, payment in full as if the work had been entirely performed, for the owner may have cancelled the contract because such payment would be beyond his means. Article 1794 of the Code Napoléon allows the owner to cancel the contract

en dédommageant l’entrepreneur de toutes ses dépenses, de tous ses travaux et de tout ce qu’il aurait pu gagner dans cette entreprise;

[Page 26]

it does not mention other damages. The codifiers in their report make no special mention of art. 1691 C.C., being content to say that

the articles numbered from 78 to 84 (art. 1691 to 1697 C.C., while they express the existing law, coincide substantially with the articles of the Code Napoléon cited under them.

The coincidence, in so far as art. 1691 C.C. is concerned, is certainly not very marked, and, in my opinion, while the French code has laid down a definite rule as to the basis of assessment of damages, our code has done so only in regard to “actual expenses and labour.”

Pothier, Louage, no. 440, Bugnet ed., vol. 4, pp. 147, 148,

to whom the codifiers refer under art. 1691 CC, says:

Par exemple, si j’ai fait marché avec un entrepreneur pour la construction d’un bâtiment, et que, depuis le marché conclu et arrêté entre nous, je lui déclare que je ne veux plus bâtir, et que je demande en conséquence la résolution du marché, l’entrepreneur ne peut pas s’opposer absolument à la résolution du marché, et prétendre que je doive lui payer le prix entier du marché, aux offres qu’il fait de remplir son obligation, et de construire le bâtiment porté au devis; car il a pu me survenir, depuis la conclusion de notre marché, de bonnes raisons pour ne pas bâtir, dont je ne suis pas obligé de rendre compte; il a pu me survenir des pertes dans mes biens, qui me mettent hors d’état de faire la dépense que je m’étais proposée. Mais si je dois être reçu à demander la résolution du marché, ce ne peut être qu’à la charge de dédommager l’entrepreneur, s’il souffre quelque dommage de son inexécution; puta, si avant que je lui eusse déclaré mon changement de volonté, il avait déjà fait emplette de quelques matériaux qu’il sera obligé de revendre à perte; s’il avait déjà loué des ouvriers qui lui deviennent inutiles. On doit aussi comprendre, dans les dommages et intérêts de l’entrepreneur, le profit qu’il aurait pu faire sur d’autres marchés que celui dont on demande la résolution lui a fait refuser.

Pothier’s reference to claims which may be considered under the head of damages, is clearly only by way of examples. Our code, as I have said, is definite merely with regard to “actual expenses and labour,” but I think it may be stated that Pothier’s refusal to allow the contractor to claim

le prix entier du marché aux offres qu’il fait de remplir de sa part son obligation

holds good under the true construction of art. 1691 C.C.

Coming now to the appellant’s claim of $35,000 under clause 8 of the agreement, it is therein expressly stated that this sum is to be paid to it

as their recompense for superintending the construction and completion of the vessel.

[Page 27]

This supposes that the appellant has exercised this superintendence until full completion of the vessel, which of course would include the installation of the engines, boilers and machinery “which are to be furnished by the company (the respondent),” and that it supplied and installed

the necessary piping and valves to connect to the hull piping, sea-suctions and discharges.

In other words, this “recompense,” with the special price I stipulated for installation of engines, boilers and machinery and the supplying and installation of the necessary piping and valves, may be assimilated to what Pothier calls “le prix entier du marché.” In my opinion, only the part of this “recompense” which corresponds to the actual “superintendence” can be allowed either as damages or as “actual expenses or labour,” and I think it comes better under the heading of “damages,” for, under reserve of the question of the “sea chest” to which I will presently refer, it is not contended that all actual expenses and sums spent for labour or materials were not paid by the respondent.

I do not think the judgment of the Superior Court can be restored, for it awarded to the appellant the whole of the sum payable for superintending the construction until full completion of the vessel. There is however room for a difference of opinion whether an allowance of approximately one-third of the $35,000 is sufficient compensation for damages suffered by the appellant by reason of the cancellation of the contract under art. 1691 C.C. The question, however, whether any damages at all should be granted, and, if so, what should be their amount, are questions to be determined by the court under this article. The Court of King’s Bench came to the conclusion that the appellant was entitled to damages, and granted it the sum of $12,000, and this court does not interfere with the quantum of such damages unless a wrong principle has been followed by the court in assessing them. This has not been shewn. I therefore do not feel justified in increasing the award with respect to these damages.

I may add that I do not find the proof satisfactory as to the portion of the “recompense” which can be said to correspond to the superintendence actually exercised. The appellant’s witnesses say that the expenditure up to the launching amounted to $350,000, and that ten per cent of

[Page 28]

this would be a fair compensation. This is not the proper test when dealing with an express contract stating for what superintendence the $35,000 is to be paid.

Both courts, including Mr. Justice Tellier who dissented, were of the opinion that the appellant had not sufficiently proved its claim for $25,000 for loss of the profit it would have made in installing the boilers, engines and machinery under clause 7 of the contract. In that I agree, but as to such a claim, it would suffice to say that the profit which the workman would have made, had the contract gone on to completion, is not, under art. 1691 C.C., the proper basis for the assessment of his damages. That, I have already stated, is clearly the effect of the article.

The appellant also claims that it is entitled to $2,896.70, which it expended in building a “sea chest” in connection with the carrying out of clause 7 of the contract. The “sea chest” was delivered to the respondent but was never paid for.

This the respondent does not deny, but its objection is that this amount was not specifically claimed in the action. The appellant admitted that in the argument before the Superior Court these expenses were overlooked. It seems to me that as this “sea chest” was really made and delivered to the respondent, it would be only fair to add the amount of the expenditure to the $12,000 granted by the Court of King’s Bench.

With this variation, I would dismiss the appeal with costs.

Appeal dismissed with costs.

Solicitor for the appellant: C. A. Barnard.

Solicitors for the respondent: Béïque & Bissonnette.